Prime cost contract
Prime cost contracts (such as JCT PPC 11) are sometimes called cost plus contracts or cost reimbursement contracts.
Prime cost contracts are used where an early or immediate start on site is required even though design information is not complete.
This method of procurement is not generally recommended, but it can be useful under particular circumstances where an immediate start on site is necessary (for example for urgent alteration or repair work, or if there has been a building failure or a fire, requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business).
Tendering proceeds based on an outline specification, any drawings and an estimate of costs. The contractor is paid the prime cost (the actual cost of labour, plant and materials) and a fee for overheads and profit. The fee can be agreed by negotiation or by competition, and may be a lump sum (which it may be possible to adjust if the actual cost is different from the estimate), or a percentage of the prime cost (which it may be possible to revise if the client changes the nature of the works).
Other basis for payment are possible, including combinations of lump sum and percentage fees. For example, it might be possible to fix some elements of overheads whilst applying a percentage to other elements and to profit.
This is a high risk form of procurement for the client as they are reliant on the contractor working efficiently and procuring sub-contracts economically. Sub contracts may be procured competitively, but there may be little incentive for the contractor to secure or select economic bids. Some of these difficulties can be mitigated if a partnering relationship has been established between the client and the contractor.
NB: Some people consider that a cost reimbursable contract or cost plus contract is one in which the client takes all the risk, whereas a prime cost contract is one in which the cost of the works packages (the prime cost) are reimbursed but the main contractor takes a risk on staffing, overhead costs and profit which might be tendered on a fixed price.
[edit] Related articles
Featured articles and news
Designing sustainability and performance into buildings
Specifying and selecting sustainable resilient timber products.
Modifying wood to improve resistance to decay and movement.
A last minute, long look for built environment professionals.
The architecture of creative reuse. Book review.
Installing solar panels on listed structures.
Sustainable development global goals, history in progress?
"Unless we act now, the 2030 Agenda will become an epitaph for a world that might have been."
Mike Kagioglou FCIOB named CIOB President
'Sustainable Development Goals must be focus for construction'
BSRIA training; a look at what's on offer
From energy management to compliance training.
TESP video warns to beware of rogue trainers.
Highlighting the slippery tactics of non-approved providers.
New Building Safety Wiki launched
Boosting awareness and understanding of the new fire safety regime.
New playbook on AI in construction published by CIOB
How to get to grips with, and the best from AI.
Digital Construction Report NBS
BIM, cloud, off-site, immersive tech, AI, twins and sustainability.
ECA learning zone and industry focus video series
From updates and amendments to circular economy, emergency lighting and much more.
Comments
For small alternation project of 8 storey building, what is the advantage of using prime cost contract?
Unless an immediate start is needed - for example if there is some danger or urgency, it is difficult to see what the advantage would be over a traditional contract.